Phantom Plumber showed up sometime between 2:30 pm yesterday and 9am this morning and finished the gas line replacement. He didn't call to say he was coming or that he had been there and finished.
Tile boy says he will be there Sunday am (early) to grout.
Furniture's on order, 3 week estimate.
Contractor made boxes for the new electrical panel and the water heater, protection from the salt air, elements etc, I "painted" them (I slop more than paint)
Tip toeing to the finish line!